This FY 2024-2025 Capital Improvement Program (CIP) Project will see the installation of stormwater trapping materials under Executive Drive. The project will take place on Executive Drive from Madison Street to Quincy Street as well as Plaza Court. The proposed improvements are intended to rehabilitate the roadway, update public utilities, and reduce flooding.  

An initial construction notice was sent to businesses/residents most impacted by the project in early February.

The anticipated start date of the project is February 12, 2024. Executive Drive will become one-way, westbound traffic only, as of Monday, February 26th. For eastbound traffic, please follow the posted detour route. Use caution when traveling through the work zone and take alternative routes when possible. The project schedule is listed below, weather permitting.

Project Schedule

February:           Mobilization and temporary pavement construction

March & April:  Storm sewer and water main construction (north side of Executive Dr and west side of Plaza Ct)

May:                   Finish storm sewer, curb & gutter, and pavement base course (Plaza Ct)

June:                 Finish storm sewer, curb & gutter, and pavement base course (Executive Dr)

July:                  New asphalt pavement, parkway restoration, de-mobilization